Lao Dam collapse, Kokuminous Room, related department meeting 2018.10.15 EDCF project Although it is not eligible for bidding
 
 
 
De
 
SK Construction Leaves July
Constructed the collapsed Lao Dam
"SK pursued profits by forcibly shortening the construction period
and changing design etc."
The allegation that it is raised raises discussion.
 
Government funds were invested
"Official development assistance '(ODA) project,
but sincere construction Focused on early completion, 'bad construction'"
I brought up my own argument
It is pointed out that.
 
The State Coordination Office will come
Opening the relevant department meeting on 16th
We are planning to check the current situation of the accident survey
that the Lao government is underway.

15th National Assembly Planning Finance Committee Affiliation
Kim Economic Cooperation Both Democratic Party members secured
SK construction of
Looking at the 'Document of the 2012 Intensive Management Society'
PNPC which is Lao PD's enforcement company
"August 2012 signed a major condition agreement
to make construction cost $ 680 million."
 
In addition to the construction fee in the agreement
"Guaranteeing SK construction with administration fee and profit
of 83 million dollars (12.2% of construction cost)
Construction cost reduction associated with design change
of 28 million dollars is provided for SK construction,
Incentive bonus payment separately at early completion
"
It contains contents such as.
 
Since then SK Construction
November 2012 Hosting a central management meeting
"Making the utmost use of design change right,
Secure 120 billion dollars at 15% level of construction cost
"
 SK made a strategy to do.
 
Continuing
"▲ dam format, change in construction material,
adjustment for pardon inclination (Keikyu) adjustment
▲ Design deformation item When reflecting
the contract Incentive granted to designers (Buyeo)
▲ Separately additional construction cost of 19 million dollars is added
"
SK made a detailed plan such as.
 
Construction delayed seven months
but freshwater period two months earlier.
 

The part that Rep. Kim raises the most suspicion is

"Although construction began in November 2013,
which was originally delayed by 7 months from the plan,
The freshwater period initially decreased
from six months to four months. "
That is the point.
 
"Reduced freshwatering period by force to get a bonus"
It not that  is It ?
 
SK Construction and PNPC
"In the final contract in November 2013"
If early fresh water is made before August 1, 2017,
We added a condition that
"incentive bonus 20 million dollars will be paid"
That's it.
 
Lao Dam business
Unlike general overseas construction projects,
in that ODA funds are introduced
The Early Freshwater Bonus Payment Contract Should Be Cautious
Rep. Kim pointed out.
 
Rep. Kim
"Sincerity For compliance construction and social
and environmental benefits security for submerged residents
Do not give incentives,
for SK construction participation invitation and profit security
Government will provide incentive bonus to early freshwater
It is difficult to convince what I accepted "
Rep. Kim said.
 
"Changed basic design to pursue profit"
Suspicion that It came out.
 
"The height of five auxiliary dams
on the basic design drawing is 10 to 25 m"
However,
"In fact it was constructed from 3.5 to 18.6 m"
Rep. Kim saying that.
 
Rep. Kim
"SK Construction Internal Document
on Construction Cost Reduction Details Plan
Design changes etc. were intensively discussed
"
As
"Auxiliary dam height is about 6.5 cm low in bulk from the time
of basic design at the construction stage
It is not irrelevant to the construction cost reduction strategy
that it is low "
He said.
 
However
In the construction industry there are many reactions
that basic design changes can be trade-enabled.
 
An officer of a large construction company
"There are no major problems as basic design changes
are made under approval while the order placement is supervised"
As
"Even if it is said that the auxiliary dam height is lowered, it conforms
to the design standard
If we look for alternatives in other ways
it will be difficult to look at the problem "
He said.
 
SK construction also
"Basic design is concept level to judge business performance"
While
"However, because the current Laotian government is investigating
the incident, we can not clarify any more"
SK said.
 
Budget executed quickly without deliberation
of the National Assembly.
 
Budget formation of Lao Dam business is also
It was found to be made opaque.
 
Government support for Lao Dam business was decided
 
May 2015
Uzbekistan Educational Information Technology Secondary Project
Mozambique public management information construction project,
Vietnamese rengan and hemp eru Igan water resources development project
And support for the Vice Minister of Developing Countries was also decided.
 
However,
"The Planning and Finance Department
Just hastening the Lao Dam business alone,
we allocated 41.1 billion won budget and enforced it. "
 
Mr. Kim said "
As for the other three projects, as stipulated in the Basic Law
for International Development Cooperation,
After discussing the National Assembly budget and deliberating the project under the affairs of the State Development Principle Office under the International Development Cooperation Committee
Began to support loans from 2016 "
As
"The Lao Dam project is the only parliamentary budget deliberation
International Development Cooperation Committee Omitted
project deliberation "
He said.

Along with this,
It is an atmosphere where the discussion on the construction failure
of Laos dam reexploses again.
 
Shim Sang-jong Justice Party Representative
On the 16th Korea National Examination Bank Export & Import Bank audit
To ask for reasons such as Laos dam accident etc
We applied for Ann Jae Hyun SK Construction President as a witness.
 
However,
"Anne representative
I submitted a reason for absence due to local activities in Laos
. "
 
The same day 's office is related to Laos dam accident (thought)
Meet relevant department meetings.
 
A government official
"In the beginning of the fall collapse accident in July was presided over
by the State Affairs Coordination Office
Relations Department Emergency Countermeasure Conference
was often held "
As
"Recently the results of the survey
of the Lao government have been mainly shared in writing (West side)
It seems that it will be reopened
if it is mentioned in the government inspection audit etc. "
He said.
 
 
Although SK construction is not eligible to bid for the Foreign Economic Cooperation Fund (EDCF) project,
SK assumed the dam construction in Laos.
 
BTS members famous for atomic bomb T-shirts 
are crazy inside the bus
Videos leaked!
https://twitter.com/i/status/1062852872176451584
Overseas fans seem to be exactly the same
Suddenly overflowing with compliments of English praise. Creepy

 

 

http://www.ekn.kr/news/article.html?no=398456


https://news.v.daum.net/v/20181106030037589

http://www.koreaherald.com/view.php?ud=20181114000854

 

 
A song called BTS "run". Members are suffering in waters in the water.
MV release date, March 11, It is the day of the Great East Japan Earthquake.
I can not forgive as a Japanese citizen.
 
BTS wearing a comfort Woman wear
Dokdo is also doing anti-Japanese act of singing our territory
.

 

The capital flight started
World stock price / Korea KOSPI
Do not move, government intervention,
Trading suspension, circuit breaker activation,

power off of server,

Koria have a proven track record.

 

Yuzuru Sato
Korea attacks Japan by combining hands with North Korea and China
Propaganda neglect affects the recreation of the comfort women problem,

the activities of Japanese companies around the world
Possibility of losing in the image strategy at the US jury trial.