目の前に企業競争はますます激しくなって、情報技術も更新しつつあります。企業のマネージャー達はもう新技術の採用、社員の育成訓練と人材の保留が企業が長い間の発展と成功に肝心なことを意識しました。しかし、社員が正しくて有効な知識を身に付けるのを判断することもうマネージャー達にとって直面しなければなりません挑戦である。  この企業競争情勢の要求に応じて、IBM会社の認証専門テストセンターはIBM会社の製品によって各種の試験科目を設計しました。AIX、AS/400、OS/2、DB2、Client/Server、VisualAge Application DevelopmentとLotusなどが含めています。もう多くの企業は社員にIBM TIM の認証試験に参加させました、専門の認証は従業員の技術レベルを高めるだけではなくて、企業の市場競争力も強めました。
000-093の問題集みんなと分かち合います
1.A manager interacts with an expense application via a human task. What action is appropriate to
take if an obscure exception occurs when the manager enters a response and completes the task?
A.Edit the business data from Failed Event Manager and re-submit the failed event.
B.Resubmit the failed event with trace using Failed Event Manager for further troubleshooting.
C.Delete the failed event from Failed Event Manager, then stop and re-start the TaskContainer.
D.Query the failed event using Failed Event Manager, then send the information to the developer.
Correct:B
2.The SystemOut.log indicates that the installation of an enterprise application failed. If the
application contains WebSphere Adapter artifacts, what must be done before attempting to
reinstall?
A.Remove any SIBus destinations or JCA activation specifications created prior to the failure.
B.Remove the Event Archive table created prior to the failure.
C.Create new Endpoint Listener to replace the one existed prior to the failure.
D.Create necessary SIBus destinations and JCA activation specifications manually.
Correct:A
3.Creation of a new profile failed with following error: Wait until the current creation or deletion
operation is complete before continuing. In order to proceed with new profile creation, what must
the administrator do next?
A.Stop the server, then restart the Profile Wizard.
B.Terminate any running javaw.exe process.
C.Make sure to enter a unique profile name from the wizard.
D.Delete profileRegistry.xml_LOCK file to release the lock.
Correct:D
4.An event failure occurred due to wrong date format which was sent from component A to
component B. What will the Failed Event Manager allow an administrator to do?
A.Edit the date value and resubmit
B.Create a human task to notify the event originator
C.Bypass component B
D.Re-route the message
Correct:A
5.When using WebSphere Process Server V6.0.1, the installation of a business process that was
generated for WebSphere Process Server V6.0.0 throws UnexpectedFailureException exception.
Which of the following must the administrator do next?
A.Regenerate business process code in V6.0.1 and reinstall.
B.Run serviceDeploy tool to resolve this problem.
C.Make sure that Business Process Container has been installed.
D.Rename the module containing the business process different from the previous version.
Correct:A
6.The TaskContainer application failed to start due to missing SchedulerCalendars application.
Which of the following tasks must the administrator complete to correct the situation?
A.Reinstall Human Task Container which will reinstall the SchedulerCalendars application.
B.Manually install the SchedulerCalendars application, which is available in \installableApps directory.
C.Reconfigure the human task container to use Application Scheduler instead.
D.Running bpeconfig.jacl will make SchedulerCalendars application accessible from TaskContainer
application.
Correct:B
7.The installation of a business integration application fails. The server log displays a message of
the form: ... BPED0202I: Validated process model 'OrderProcess' unsuccessfully: 0 information, 2
warnings, 1 error. What should the administrator do to complete the application installation?
A.Turn detailed tracing on and install again to capture details on the installation failure.
B.Update the validFrom value for the OrderProcess component and reinstall.
C.Return the application to developer to fix errors in OrderProcess.
D.Return the application to developer to rebuild staging projects.
Correct:C