After directives by urban development (UDH) minister Shanti Dhariwal to increase the workforce to expedite the Jaipur Metro project, the firm contracted by the Delhi Metro Rail Corporation (DMRC) continues to struggle in absence of adequate funds.During his visit to the Metro work sites on last Friday, Dhariwal directed the contractors to increase the number of labourers at the sites to ensure that the work is carried out round the clock so that the project meets the fresh deadline of July 30.However, a well-placed source in the DMRC informed that so far, the number has not been increased.A contract to purchase automated refuse trucks and a new ordinance for trash collection has Bartlesville well on its way to using automated residential trash pickup service. "The firm is facing financial crunch and it will be a difficult task to increase the labourers in the near future.Our frozen mushroom also gives option of relishing the taste of mushroom in each and every season giving its natural taste all the time. There is shortage of at least 150 to 200 labourers and it requires a huge capital to recruit them,www.ceectrucks.com is a sewage suction truck manufacturer." the source said.On the other hand, DMRC, general manager Atul Gadgill said, "It takes time to procure specialized labourers. It is under process and will be completed within a week.http://www.ceectrucks.com/ with international management systems of technical development, manufacturing processes and logistics, as well as strong sales network and perfect service system covering the whole domestic market and extending to the oversea market.Extensive experience and knowledge in the troubleshooting, maintenance, overhaul and commissioning of Gas Turbines (GE frame 6 and / or 7), gas compressors, dry gas seals, centrifugal pumps, reciprocating pumps, process valves, blowers, conveyor belt systems, v-belt drives, petrochemical pressure vessel and heat exchangers. The labourers on two launching girder has been increased."The minister had set May 30 as the deadline for completion of civil construction work. For the civil work from Mansarovar to Chandpole, nearly 300 labourers are employed in the 12-hour shift. He had directed that construction for the Jaipur Metro should now be carried out 24 hours a day in two shifts, in a bid to meet the deadline of July 30."Hiring labourers to meet the deadline is not going to be easy for the authorities as several of them have migrated to Delhi and are working with the Delhi Metro, the source said, adding, "Workers from Jaipur in the recent past have joined the Delhi Metro project. It is against the policy and DMRC cannot provide work to such labourers. If this trend is not checked, it will be a major challenge for the Jaipur project."Officials also informed that in the absence of skilled workforce, optimum utilization of the advanced machinery is not possible.A senior JMRC official said, "On one launching segment, 12 expert workers are required in one shift. To meet the deadline there is an urgent requirement of 24 workers so that work can be done throughout the day else despite the required machinery, the project can't be completed on time."The UDH minister has now announced that the train will be operational between Mansarovar and Jaipur railway station by the July end.